Skip to content
Kairos scheduling handbook

Learn the schedule. Defend the decision.

A practitioner-built handbook for the people who plan, review, update, and rely on construction schedules—from CPM mechanics to delay analysis.

46practitioner guides
143plain-language terms
16source records

First-wave field guides

Start with the decision your schedule must support.

Foundation

Critical path method (CPM)

The calculation behind nearly every construction schedule — and what "critical" actually means.

Read the guide →
Foundation

Total float (and free float)

How far an activity can slip before the project finish moves — and why float is where schedules get gamed.

Read the guide →
Foundation

Baseline schedule

The approved plan every later update is measured against — and the document delay disputes come back to.

Read the guide →
Foundation

Data date

The "as-of" line in a schedule update — everything before it is history, everything after it is forecast.

Read the guide →
Foundation

Logic ties and lags

FS, SS, FF, SF and the lags between them — the relationships that make a schedule a network instead of a list of dates.

Read the guide →
Foundation

Work breakdown structure (WBS)

The hierarchy that decomposes a project’s scope into the levels a schedule — and its reporting — hangs from.

Read the guide →
Intermediate

Schedule quality

Whether a schedule can be trusted as a forecast — judged from its mechanics, not its promises.

Read the guide →
Intermediate

Negative float

What it means when a schedule reports less than zero slack — and why it demands an answer, not a shrug.

Read the guide →
Intermediate

Schedule constraints

Date pins that override logic — sometimes necessary, often a way to make a schedule say what someone needs it to say.

Read the guide →
Intermediate

Out-of-sequence progress

Work reported in a different order than the logic says — a small flag that often reveals a plan no longer being followed.

Read the guide →
Intermediate

Monthly schedule update

The contractor’s periodic progress submission — the heartbeat of schedule control and the record claims are later built from.

Read the guide →
Intermediate

Look-ahead schedule

The two-to-six-week slice of the plan used to run the work — where the master schedule meets the field.

Read the guide →
Advanced

Delay claims, explained

Excusable, compensable, and critical delay—distinct questions that must be tested against the contract, facts, and governing law.

Read the guide →
Advanced

Concurrent delay

When owner and contractor delays overlap — the most contested question in delay analysis.

Read the guide →
Advanced

Time impact analysis (TIA)

A forward-looking method for modeling an event, inserting it into an appropriate contemporaneous schedule, and comparing the calculated effect.

Read the guide →
Advanced

As-planned vs as-built analysis

The retrospective comparison of what was promised against what happened — intuitive to show, hard to prove causation with.

Read the guide →
Advanced

Fragnet

A small network fragment modeling one change or delay event, inserted into the schedule to measure its effect.

Read the guide →
Advanced

Extension of time (EOT)

A contractual mechanism for adjusting a completion obligation when the governing agreement permits time relief.

Read the guide →
Intermediate

Schedule performance index (SPI)

Earned value’s schedule ratio — a useful trend and a dangerous single number.

Read the guide →
Intermediate

Earned value, in plain terms

PV, EV, AC and the ratios built on them — progress measured in value rather than dates.

Read the guide →
Intermediate

Float consumption

Tracking how fast a path’s slack is being spent — the earliest honest warning most schedules give.

Read the guide →
Intermediate

DCMA 14-point assessment

A widely referenced schedule-mechanics screen—what the fourteen measures catch, and why thresholds are not acceptance criteria.

Read the guide →
Intermediate

Schedule compression: crashing and fast-tracking

The two levers for recovering time — paying for speed, or accepting overlap risk — and what each does to a schedule.

Read the guide →
Intermediate

Schedule risk analysis (Monte Carlo)

Replacing single-point durations with ranges to see the odds behind a finish date.

Read the guide →
Foundation

P6 Professional interface orientation

A professional map of the Projects and Activities workspaces—what each pane controls and where to verify the schedule.

Read the guide →
Foundation

Create and govern a P6 project

Set up the EPS location, project identity, dates, calendar, defaults, security, and coding before detailed planning begins.

Read the guide →
Foundation

Build and audit P6 calendars

Create project calendars, define shifts and exceptions, assign them deliberately, and verify their effect on dates and durations.

Read the guide →
Foundation

Structure WBS and activity codes in P6

Create a scope hierarchy and controlled coding system that supports planning, responsibility, reporting, and exchange.

Read the guide →
Foundation

Create activities, types, and durations in P6

Turn scope into measurable activities with stable IDs, clear names, suitable types, calendars, duration types, and progress rules.

Read the guide →
Intermediate

Build and verify logic in P6

Create predecessor and successor relationships, inspect driving ties, control lags, and eliminate unsupported open ends.

Read the guide →
Intermediate

Set the data date and schedule a P6 project

Run a controlled F9 calculation with the right data date, options, completion condition, and retained schedule log.

Read the guide →
Intermediate

Create, assign, and protect P6 baselines

Capture the accepted plan, assign the correct comparison baseline, display it, and control later updates or replacements.

Read the guide →
Intermediate

Status and update a P6 schedule

Collect defensible actuals, reforecast remaining work, advance the data date, calculate, compare, and publish a complete update record.

Read the guide →
Intermediate

Build professional P6 layouts, filters, and reports

Create controlled views for planning, status, critical paths, baseline comparison, quality review, and stakeholder reporting.

Read the guide →
Intermediate

Run and disposition P6 Check Schedule

Screen logic, lags, constraints, float, durations, progress, baselines, closed-project links, and out-of-sequence work.

Read the guide →
Advanced

Import, export, and validate P6 XER files

Exchange native schedule data without losing lineage, overwriting global data blindly, or mistaking a successful import for parity.

Read the guide →
Advanced

Assign resources and costs in P6

Load resources, roles, units, rates, expenses, and accrual rules without allowing calculation settings to rewrite the plan silently.

Read the guide →
Advanced

Calculate multiple float paths in P6

Expose the controlling and near-controlling paths to a selected milestone instead of reporting one critical chain only.

Read the guide →
Foundation

Schedule basis memorandum

Document the planning rules, assumptions, calendars, coding, logic, resources, constraints, and calculation settings behind the schedule.

Read the guide →
Intermediate

Construction calendar governance

Control workweeks, shifts, holidays, weather, possessions, shutdowns, and P6 assignments as managed schedule data.

Read the guide →
Advanced

Baseline review and acceptance playbook

Gate scope, logic, calendars, durations, contract dates, resources, quality, narrative, and approval before freezing the plan of record.

Read the guide →
Intermediate

Monthly schedule update governance

Operate a repeatable cutoff, status, change, calculation, review, response, and approval cycle.

Read the guide →
Advanced

Schedule change-control playbook

Separate progress from revisions, authorize consequential edits, preserve before-and-after files, and keep the baseline yardstick intact.

Read the guide →
Intermediate

Schedule quality thresholds and exception management

Set project-specific screening thresholds, investigate exceptions, and trend the quality of the native schedule without gaming the score.

Read the guide →
Advanced

Schedule recovery-plan playbook

Convert a missed forecast into specific, resourced, risk-tested actions with measurable recovered days and approval gates.

Read the guide →
Foundation

Schedule records and audit-trail handbook

Preserve native files, calculations, narratives, evidence, comments, decisions, and exchanges so future reviews can reconstruct what happened.

Read the guide →