Key takeaways
- When the scheduler advances the data date and records progress, the software re-plans all remaining work forward of that line.
- Three checks catch most abuse.
What the data date controls
When the scheduler advances the data date and records progress, the software re-plans all remaining work forward of that line. The forecast finish, the float values, the critical path — all are computed as of the data date. An update is really a statement: "as of this date, here is what happened and here is what the logic now implies."
The failure modes to catch
Three checks catch most abuse. First, staleness: an update with a data date weeks older than its submission date is reporting old news as current. Second, progress on the wrong side of the line: activities showing actual dates after the data date, or planned work still sitting before it, mean the update was not statused honestly. Third, a data date that does not match the agreed reporting cutoff makes period-over-period comparison quietly wrong.
None of these require judgment calls — they are mechanical, and they are exactly the kind of check that should run on every submission before anyone reads the narrative.
Sources and scope
Follow the reference trail.
This guide is original educational commentary. Kairos reference records identify the source organizations, editions and scope behind this guidance. The original publishers retain their publications and rights.
10S-90: Cost Engineering TerminologyAACE International · checked 2026-08-01Primavera P6 Professional User Guide, Version 26Oracle · checked 2026-08-01Schedule Assessment Guide: Best Practices for Project SchedulesU.S. Government Accountability Office · checked 2026-08-01UFGS 01 32 01.00 10: Project ScheduleWhole Building Design Guide / U.S. Department of Defense · checked 2026-08-01