Key takeaways
- Slippage does not hit the completion date until a path runs out of float; until then, the network silently absorbs it.
- The mechanic is simple: for each significant path or work area, compare total float across consecutive updates and flag the largest drops.
Why finish dates lag reality
Slippage does not hit the completion date until a path runs out of float; until then, the network silently absorbs it. A path that entered the period with forty days of float and exits with twelve has had a bad month that no milestone report will show. Watching only dates means discovering problems at the exact moment they become expensive.
Measuring the burn
The mechanic is simple: for each significant path or work area, compare total float across consecutive updates and flag the largest drops. Rate matters more than level — forty days of float burning at ten a month is four months from critical, and that arithmetic is the early warning. Persistent burn concentrated in one area is a localized problem; broad burn across many paths is a plan losing its buffer everywhere at once, which is a different and worse conversation.
This is also a check on the update itself: float restored without explanation — logic loosened, a lag shortened, a constraint added — is how a bad month gets made to look survivable. Where the float went, and why, belongs in every period review.
Sources and scope
Follow the reference trail.
This guide is original educational commentary. Kairos reference records identify the source organizations, editions and scope behind this guidance. The original publishers retain their publications and rights.
10S-90: Cost Engineering TerminologyAACE International · checked 2026-08-01Schedule Assessment Guide: Best Practices for Project SchedulesU.S. Government Accountability Office · checked 2026-08-01Delay and Disruption Protocol, second editionSociety of Construction Law · checked 2026-08-01