Submittal register template

Connect required submissions, review dates and the work that depends on them.

Kairos OneKnow sooner. Act faster.

Download Excel workbook · September 2026 / v1.0 · No account required

Before you start

Use to coordinate required design, product, method or closeout submissions. Tailor status names, review periods and authorities to the contract before use.

  • Submittal requirements and specification sections
  • Procurement and construction need dates
  • Review periods and approving authorities
  • Transmittals, revisions and disposition records

How to use it

Build the required inventory

List each package with a specification reference and responsible submitter. Split packages when they have different reviewers, need dates or dispositions.

Work back from the need date

Allow for preparation, review, resubmission, fabrication and delivery. The register records agreed review dates; it does not automatically calculate contractual review periods.

Keep revision and disposition traceable

Link each submission and return to its transmittal. Use the reporting date to identify overdue review commitments and resolve missing dates before relying on the exception list.

Fields included

  • ID
  • Package / specification
  • Submitter
  • Review authority
  • Required on site
  • Review due
  • Submitted
  • Status
  • Days overdue
  • Revision / disposition reference

A review ahead of procurement

Illustrative example: the controls panel shop drawing must be reviewed before fabrication is released. The register records the specification section, required-on-site date, reviewer and agreed review due date. An overdue flag prompts follow-up; it does not change the approval status.

Before issue

  • Every required package has a specification reference.
  • Review dates support the actual procurement or work need.
  • Revision and disposition records remain traceable.
  • The register does not imply approval from elapsed time.

Practice references

  • UFGS 01 33 00, Submittal Procedures, August 2026

Original Kairos working templates informed by common project-controls practice. Adapt them to your contract, project procedure and approval authority. They are not official standards-body forms or a certification of compliance.