Download Fillable PDF · September 2026 / v1.0 · No account required
Before you start
Use before incorporating a material logic, calendar, scope or duration change into a controlled schedule. Follow the contract's notice and change provisions separately.
- Event description and contemporaneous records
- Unaltered comparison schedule and data date
- Proposed activities, logic and assumptions
- Applicable change procedure and decision authority
How to use it
Describe the event before the effect
State what happened, when it became known and which work may be affected. Keep facts, assumptions and disputed matters distinct.
Document the proposed model
Identify activities, calendars, relationships and durations to add or amend. Preserve a comparison file and describe the analysis method and any limitations.
Route and retain the decision
Record the required decision and authorized reviewer. Track the approved implementation revision separately from any entitlement or compensation decision.
Fields included
- Event / date identified / notice reference
- Comparison schedule / data date
- Affected activities and interfaces
- Proposed logic, calendar or duration changes
- Assumptions / analysis method / evidence
- Forecast milestone effect / remaining uncertainty
- Requested decision / authority / required date
- Disposition / implementation revision / record reference
Revised access to a work area
Illustrative example: a revised access window affects trenching activity CIV-220. The request records the access instruction, proposed calendar revision and the comparison schedule. A seven-day forecast movement is described as an analysis result pending review, not an approved extension of time.
Before issue
- The comparison file is retained without modification.
- The proposed change is reproducible from the listed inputs.
- Forecast effect is not presented as an entitlement decision.
- Approval and implementation references are recorded separately.
Practice references
- UFGS 01 32 01.00 10, Project Schedule, August 2026
- GAO Schedule Assessment Guide, GAO-16-89G
Original Kairos working templates informed by common project-controls practice. Adapt them to your contract, project procedure and approval authority. They are not official standards-body forms or a certification of compliance.