Change & recovery / K1-CH-02

Schedule recovery plan template

Set out a feasible recovery proposal with workface assumptions, resources, constraints and review points.

Kairos OneKnow sooner. Act faster.

Download Fillable PDF · September 2026 / v1.0 · No account required

Before you start

Use when a forecast delay requires a recovery proposal. Treat recovery as a plan to test and monitor; it is not a promise of achieved acceleration or a decision on liability.

  • Current statused schedule and contractual milestones
  • Documented causes and constraints
  • Resource, access, procurement and workface availability
  • Safety, quality and approval requirements

How to use it

Define the shortfall

Identify the affected milestone, current forecast and credible driving path. Confirm that proposed measures address the work actually controlling completion.

Test the recovery measures

Describe resequencing, additional capacity or changed work methods with their resource and interface assumptions. Check safety, quality, procurement and calendar feasibility.

Monitor against evidence

Set measurable weekly commitments and escalation triggers. Review actual production against the plan and retain approval references for any adopted schedule changes.

Fields included

  • Affected milestone / current forecast / target
  • Driving activities / cause / evidence
  • Proposed recovery measures and sequence
  • Resources / productivity basis / access assumptions
  • Safety, quality and procurement constraints
  • Model comparison / residual exposure
  • Weekly commitments / measures / escalation trigger
  • Owners / approvals needed / review date

A measurable second workfront

Illustrative example: a second cable-pulling crew is proposed for an independent area after access is confirmed. The plan records crew availability, installation quantities, testing dependencies and a weekly output target agreed by the team. The forecast gain remains conditional on those assumptions.

Before issue

  • Measures target driving or near-critical work.
  • Resource and productivity assumptions have a stated basis.
  • Access, safety, quality and procurement constraints are addressed.
  • The plan has review dates and measurable commitments.

Practice references

  • UFGS 01 32 01.00 10, Project Schedule, August 2026
  • GAO Schedule Assessment Guide, GAO-16-89G

Original Kairos working templates informed by common project-controls practice. Adapt them to your contract, project procedure and approval authority. They are not official standards-body forms or a certification of compliance.