Fictional cases for professional practice. They do not establish project acceptance or professional qualification.
Intermediate · 30-minute practice lab
Original baseline acceptance lab
Test a fictional original baseline for scope, logic, calculation, documentation, and readiness to become the project control model.
- Confirm that contract milestones and material scope are represented.
- Separate documented planning assumptions from model-integrity defects.
- Test whether the longest path is supported by complete, dynamic logic.
- Issue an acceptance recommendation tied to the stated review protocol.
Intermediate · 25-minute practice lab
Monthly schedule update review lab
Inspect a fictional monthly update, separate supported changes from forecast-integrity concerns, and issue a defensible disposition.
- Reconcile the schedule data date with the evidence cutoff.
- Distinguish documented operating changes from unsupported model changes.
- Identify conditions that can distort the forecast or critical path.
- Write a disposition that follows the stated review protocol.
Advanced · 35-minute practice lab
Prospective time-impact analysis review lab
Review a fictional change-event TIA for source-schedule integrity, fragnet logic, calculation comparability, impact reporting, and technical readiness.
- Verify that the analysis uses the appropriate accepted source schedule.
- Test whether the fragnet represents the event and connects dynamically to affected work.
- Separate modeled schedule impact from entitlement, responsibility, and compensability.
- Confirm that the result is reproducible under consistent calculation settings.